Revolution Wind installs last of its 65 offshore turbines, Connecticut officials say
Gov. Ned Lamont and the state's acting environmental commissioner said the 704-megawatt project southeast of Point Judith, R.I., has placed its final turbine and is expected to reach full commercial operation before the end of 2026. Connecticut is buying 304 megawatts of its output.
The Revolution Wind offshore project has installed the last of its 65 turbines, Gov. Ned Lamont's office said Friday, a step toward full commercial operation that the state expects before the end of 2026.
The 704-megawatt project sits about 15 nautical miles southeast of Point Judith, R.I., and began construction in 2023, according to the governor's office. Connecticut has contracted to buy 304 megawatts of its output, with the remaining 400 megawatts going to Rhode Island.
Once fully running, the project will deliver enough electricity to the New England grid to power 350,000 homes, or about 2.5% of the region's electricity supply, the state said. Connecticut's share would meet about 5% of the state's overall electricity demand.
An analysis by the Connecticut Department of Energy and Environmental Protection estimates that by 2028 the project will save Connecticut and New England ratepayers half a billion dollars a year in electricity market costs, and save Connecticut ratepayers $150 million to $200 million in public benefits charges over the life of the 20-year contract, according to the release.
Emma Cimino, the department's acting commissioner, said the state's share will "add much-needed energy supply to the New England grid" and provide "another layer of reliability and protection from price volatility" during the winter, when the regional grid is most strained.
Lamont said the milestone advances the state's effort to diversify energy production and lower electricity rates.