Lane and ramp closures planned on I-95 southbound at Broadway in Bangor
The Maine Department of Transportation will shift southbound traffic onto a new bridge over Broadway from Oct. 16 to Oct. 19, closing lanes and Exit 185 ramps in stages.
The Maine Department of Transportation will close lanes and ramps on Interstate 95 southbound at Exit 185 in Bangor from Oct. 16 to Oct. 19 as it moves traffic onto a new southbound bridge over Broadway, the department said Friday.
Crews will rebuild shoulders and mill and repave the highway so southbound traffic can be shifted off a temporary bridge and onto the new, permanent one. The work is part of the project to replace the I-95 bridges over Broadway. The department said drivers should plan for delays and detours.
The work will be done in four phases. First, the southbound high-speed lane will close while crews mill and pave both ends of it. The travel lane will stay open over the temporary bridge, and both southbound Exit 185 ramps will remain open.
In the second phase, the high-speed lane will reopen across the new bridge, while the southbound travel lane and the Exit 185 southbound off-ramp close. In the third, the off-ramp will reopen and the travel lane will stay closed; the southbound on-ramp may close if necessary. In the final phase, the travel lane will open across the new bridge and both ramps will be open.
While the Exit 185 southbound off-ramp is closed, drivers should get off at Exit 186 for Stillwater Avenue and follow detour signs down Stillwater Avenue to Broadway. While the southbound on-ramp is closed, drivers should follow signs along Broadway to Stillwater Avenue and get on I-95 at Exit 186.
Message boards will alert drivers to the closures, the department said.